SUNRACK TECHNOLOGIES LLP · PROJECT FALCON

Requirements Traceability Matrix

Living register — no requirement is yet Validated

Document ID

FALCON-GOV-004

Version

0.1

Status

Living register — no requirement is yet Validated


1. Purpose#

A requirement that cannot be traced to a test, and a test that cannot be traced to a requirement, are both waste. This matrix is the single place where that link is maintained.

It answers four questions on demand:

  1. Where did this requirement come from?
  2. Which experiment will demonstrate it?
  3. What is its current evidence status?
  4. If it changes, what else is affected?

Maintenance rule: this matrix is updated in the same change as any requirement or experiment change. A matrix that lags the documents is worse than none, because it is trusted and wrong.


2. Status vocabulary#

Status Meaning
Aspirational A target with no evidence it is achievable. Must not be quoted externally.
Derived Traced to a stated engineering need; not yet confirmed against Sunrack project practice
Confirmed Agreed against real Sunrack project requirements
Validated Demonstrated by Falcon measurement under V1-00 metrology and leakage rules
Analysed An analytical feasibility verdict exists; measurement still required

No requirement in this matrix is Validated. That is the purpose of the V1 campaign, and until then nothing here is a performance claim.


3. Measurement requirements#

ID Requirement Source Tier Verified by Gate Status Feasibility
MR-01 Roof boundary ±(25 mm + 1 mm/m) Area and module count B V1-00 RF-05, IN-04 D Derived Analysed — achievable
MR-02 Usable roof area ±2 % Proposal and BOM quantity B V1-00 RF-01 D Derived Analysed — achievable
MR-03 Plane normal ±0.5° Structural prefabrication C V1-00 IN-02, Exp. I D Derived Analysed — large margin (F-6)
MR-04 Azimuth for yield ±2° Energy estimate C V1-00 IN-02 D Derived Analysed — achievable
MR-05 Plane offset / flatness ±25 mm Packing and levelling B V1-00 IN-01, RF-01 D Derived Analysed — achievable
MR-06 Obstacle height ±50 mm Shading analysis B V1-00 RF-05 E Derived Analysed — probable
MR-07 Obstacle plan position ±100 mm Layout keep-outs B V1-00 RF-05 E Derived Analysed — achievable
MR-08 Parapet height ±25 mm First-row setback B V1-00 RF-05 E Derived Analysed — marginal
MR-09 Structural member position ±15 mm over 5 m Rail pre-cutting A Experiment H — Aspirational Not achievable optically (F-12)
MR-10 Far-field object ±500 mm at 20–50 m Surrounding shading D V1-00 RF-04 E Derived Analysed — achievable
MR-11 Absolute position ±50 mm, optional mode Site drawings, revisits B V1-00 RF-01 D Derived Achievable with control only
MR-12 Local distance ±(10 mm + 1 mm/m), L ≤ 10 m General dimensioning B V1-00 IN-01, RF-01 D Derived Analysed — marginal, key V1 question

4. Functional requirements#

ID Requirement Source Verified by Status
FR-01 Flag marginal module rows within 150 mm Tolerances §4.1 Software test Derived
FR-02 State shadow sensitivity to height uncertainty Tolerances §4.4 Software test Derived
FR-03 Detect obstacles ≥150 mm within working range Error budget §5.2 V1-00 RF-05, Gate E Derived
FR-04 Report low-point-support regions, not silent gaps Error budget §5.2 V1-00 coverage metric Derived
FR-05 Determine purlin locatability before architecture freeze Finding F-12 Experiment H Open — gates scope
FR-06 Per-point motion compensation as a specified stage Finding F-9 V1-00 Stage 3 step 7 Derived
FR-07 Edges by plane intersection, never extreme-point picking Finding F-7 V1-00 §9.1 Derived
FR-08 Boresight ≤0.05°, verified at 8–15 m Finding F-10 V1-00 Stage 2 step 9, Gate C Derived
FR-09 Every reported dimension carries an uncertainty Tolerances §3 Software test Derived
FR-10 Distinguish relative from absolute measurements Error budget §2 Software test Derived
FR-11 In-scan operator feedback on coverage and tracking Software plan §8 V1 field use Derived
FR-12 Obtain legal-metrology opinion Compliance §2 Consultant opinion Open
FR-13 Consolidated compliance campaign with CB certificate Compliance §4 Certification plan Derived
FR-14 No compliance-affecting substitution without approval Compliance §6 Contract clause Derived

5. Data requirements — procurement filters#

The first three are hard filters. A sensor failing them is disqualified for the product, whatever else it offers.

ID Requirement Source Verified by Status Filter
DR-01 Hardware timestamps with documented semantics Finding F-8 Vendor confirmation + Stage 3 Derived Hard
DR-02 Inter-sensor synchronisation better than 1 ms Finding F-8 V1-00 Stage 3, Gate C Derived Hard
DR-03 Per-point LiDAR timestamps Finding F-9 Vendor confirmation + Stage 1 Derived Hard
DR-04 IMU ≥200 Hz, documented axes and units Finding F-9 Vendor confirmation Derived Hard
DR-05 Raw or minimally processed measurement access D-005 Vendor confirmation + Stage 1 Derived Hard
DR-06 Global shutter for tracking, colour and photogrammetry Finding F-3 Official specification Derived Strong preference
DR-07 Readable, writable extrinsics with explicit frames Finding F-10 Stage 2 Derived Hard

6. Product requirements#

ID Requirement Status Conflict
PR-01 Device mass < 1 kg Aspirational Conflicts with preferred LiDAR class (F-5, D-023)
PR-02 Sensor mass < 300 g Aspirational Same conflict
PR-03 System power < 15 W Aspirational Host compute inclusion undefined
PR-04 Battery runtime ≥ 2 h Aspirational Workload undefined
PR-05 Scan duration ~1 min Aspirational Meaningless without roof area
PR-06 Maximum useful range 25 m Aspirational Tier D only, not at Tier B tolerance
PR-07 Working range 2–15 m Derived —
PR-08 Horizontal FOV ≥ 90°, vertical ≥ 60° Derived —
PR-09 Operating temperature 0–50 °C Derived May be optimistic for Indian rooftops
PR-10 Ingress protection IP54+ Derived —
PR-11 Laser Class 1 to IEC 60825-1, all fault conditions Mandatory Cannot be inherited from a component

7. Software and licence requirements#

ID Requirement Source Status
SW-01 Results traceable to dataset checksum, commit and config Software plan §5.1 Derived
SW-02 Processing in a pinned container; digest recorded Software plan §5.1 Derived
SW-03 Configuration version-controlled, not hand-edited Software plan §5.1 Derived
SW-04 Reproducible metrics from a recorded configuration Software plan §5.1 Derived
SW-05 All V1-00 metrics from one command Software plan §5.1 Derived
SW-06 Checkpoint isolation enforced in software V1-00 §7.7 Derived — highest value
SW-07 Sample size, reference uncertainty and exclusions with every metric V1-00 §8.1 Derived
SW-08 Append-only results Software plan §5.1 Derived
SW-09 No conformance claim without n and standard error V1-00 §8.1 Derived
SW-10 Percentiles flagged unstable where n < 20 V1-00 §8.1 Derived
LIC-01 No product-path component without recorded licence review Software plan §7 Derived — act now
LIC-02 R&D-only and product-path use tracked separately Software plan §7 Derived
LIC-04 Prefer permissive licences on the product path Software plan §7 Derived
LIC-07 Software bill of materials reviewed every release Software plan §7 Derived
IP-01 Freedom-to-operate search before architecture freeze IP strategy §5 Open
IP-05 Contractor IP assignment before work starts IP strategy §7 Open — act now
IP-07 Observe Indian foreign-filing restriction IP strategy §7 Open

8. Coverage check#

Experiment Requirements verified
V1-00 Stage 1 DR-01, DR-03, DR-05, Gate B
V1-00 Stage 2 FR-08, DR-07, Gate C
V1-00 Stage 3 DR-02, DR-04, FR-06, Gate C
V1-00 Stage 4 MR-05, MR-12, Gate D
V1-00 Stage 5 MR-12, trajectory metrics
V1-00 Stage 6 MR-01, MR-02, MR-06, MR-07, MR-08, MR-10, MR-11, Gates D and E
Experiment G (photogrammetry) MR-12 via path P, D-017
Experiment H (purlin) MR-09, FR-05, D-022
Experiment I (angular bias) MR-03, MR-04
Software Phase S0 SW-01 to SW-10, LIC-01

Requirements with no verification route yet#

These need either an experiment or a decision that they are out of scope. An unverifiable requirement is a defect in the requirement set.

ID Gap
FR-01, FR-02, FR-09, FR-10 Software behaviour — needs a software test plan, not a field experiment
FR-11 Needs a usability evaluation method; currently only informal field use
FR-12, FR-13, FR-14 Depend on consultant and contract work, not measurement
PR-03 to PR-06, PR-09 Cannot be verified until definitions are fixed (workload, roof area, compute inclusion)
PR-11 Needs laser classification measurement on a Falcon-specific build
MR-09 Verification route is Experiment H, which may return a negative result

PR-03 to PR-06 are the notable gap. They are currently unverifiable as written, not merely unverified — "scan duration about 1 minute" has no roof area attached, and "power under 15 W" does not say whether host compute is included. Fixing the definitions is a prerequisite to testing them, and costs nothing but a decision.

Source: docs/07-governance/REQUIREMENTS_TRACEABILITY_MATRIX.md