Proposed experiment plan

Document ID

FALCON-RD-001

Version

0.3

Status

Proposed experiment plan

Test direction

Controlled indoor mock-roof followed by an actual rooftop; independent survey reference with separate registration-control targets and held-out checkpoints.

Version 0.3 adds two things: a software workstream that can start before hardware arrives, and a forward phase plan beyond V1. Version 0.2 described V1 well but had no stated successor, which left the project without a visible path from experiment to product.

1. Objective#

Investigate the feasibility of combining one commercially available 3D LiDAR sensor and one commercially available stereo/depth camera to produce spatial data useful for rooftop solar surveying. Execute the test campaign using V1-00 as the experiment and ground-truth procedure; do not treat the earlier ±2 cm target as a frozen acceptance requirement.

2. Starting hardware#

  • One developer-accessible 3D LiDAR.
  • One developer-accessible stereo/depth camera.
  • A host computer capable of recording and processing both data streams.
  • A rigid temporary mounting frame.
  • Calibration targets/tools as required.
  • Optional IMU/GNSS components if not integrated or if experiments require independent references.

The first sensor combination is not a final product selection. It is a practical starting experiment.

3. Selection approach#

Price is not the main selection criterion for this R&D stage. Prioritize: 1. Sensor quality and repeatability. 2. Direct access to data needed for independent processing. 3. Documented SDK/API and protocol. 4. Linux support and ROS/ROS2 ecosystem where available. 5. Timestamp and synchronization capabilities. 6. Calibration documentation/tools. 7. Manufacturer support and product lifecycle. 8. Physical integration practicality.

Do not require the first prototype to meet final handheld mass, power or enclosure aspirations. Record those characteristics for future productization.

4. Initial experiments#

Experiment A — Independent sensor baseline#

  • Record LiDAR data in static scenes.
  • Record stereo images/depth in the same scenes.
  • Capture timestamps and configuration metadata.
  • Measure completeness, noise, repeatability and failure cases.

Experiment B — Calibration#

  • Determine camera intrinsics.
  • Determine LiDAR-to-camera extrinsics.
  • Evaluate calibration repeatability after remounting.
  • Record calibration method and uncertainty.

Experiment C — Synchronization#

  • Identify each device's clock and timestamp semantics.
  • Test hardware synchronization options.
  • Estimate timing offset and drift if software synchronization is used.
  • Evaluate error caused by motion and timing offset.

Experiment D — Fusion#

  • Transform data into a common coordinate frame.
  • Compare LiDAR points with stereo-derived depth.
  • Test complementary coverage and disagreement.
  • Preserve original sensor data to enable repeatable offline analysis.

Experiment E — Rooftop field test#

Use representative roofs and document: - Roof materials and surface texture. - Range and incidence angle. - Strong sunlight/shadows. - Obstacles and reflective/low-texture surfaces. - Operator movement and scan path. - Data gaps, noise and reconstruction completeness.

Experiment F — Product relevance#

Record: - Sensor/module size and mass. - Power draw and peak consumption. - Heat and thermal throttling. - Cable/interface requirements. - Compute and storage demands. - Mounting and field usability.

Experiment G — Photogrammetry over the walking baseline (added in 0.3)#

Error-budget Finding F-2: a walking operator supplies the large effective baseline that a handheld rig cannot. Structure-from-motion over a 2 m walk achieves the ~1.9 m effective baseline needed for 20 mm precision at 10 m, which fixed-baseline stereo cannot reach at any sensor quality.

  • Process the same recordings through a structure-from-motion and multi-view-stereo path (path P in V1-00 §2).
  • Compare against the LiDAR path on the same held-out checkpoints.
  • Characterise behaviour on textured versus low-texture roof surfaces — clean sheet metal is the hard case and must be tested, not assumed.
  • Record compute cost and processing time, which are the practical obstacles.

This is the experiment that stereo was wrongly expected to answer.

Experiment H — Purlin and rafter locatability (added in 0.3)#

Resolves FR-05 and error-budget Finding F-12. This experiment gates the product scope decision.

The tightest genuine tolerance in mounting-structure work is the position of purlins and rafters, because rails are pre-cut and clamps must land on structural members. On a sheet-metal roof those members lie beneath the sheet and are invisible to every optical sensor under consideration.

  • Determine whether positions can be inferred from visible evidence: fastener and screw lines, sheet profile periodicity, or sheet deflection between supports.
  • Compare inferred positions against the actual positions, established by whatever method Sunrack uses today.
  • Assess the achievable tolerance against MR-09 (±15 mm over 5 m).

A negative result is a valuable result. It tells the project that Falcon measures the roof envelope and that structural-member location stays a separate task — which changes the product claim, the customer workflow and the scope of what must be built. Discovering that after architecture freeze would be far more expensive.

Experiment I — Systematic bias in angular measurands (added in 0.3)#

Error-budget Finding F-6: plane normals should reach roughly 0.03° from random noise on a 3 m patch, against a ±0.5° requirement. Random noise is therefore not the risk for pitch and azimuth; systematic bias is.

  • Measure the same surveyed plane from multiple device orientations and standoff distances.
  • Look for a consistent offset rather than scatter.
  • Investigate candidate causes where bias appears: boresight calibration, IMU gravity-vector misalignment, incidence-angle-dependent range bias.

A test that reports only scatter on these measurands will report excellent performance regardless of whether the device has a systematic problem.

5. Test-data discipline#

For each run record: - Test ID, date, operator and site category. - Sensor model, serial number and hardware revision. - Firmware, SDK, driver and host OS versions. - Sensor settings and calibration files. - Mounting geometry and coordinate-frame definition. - Lighting/weather and target surfaces. - Range and ground-truth method. - Raw data file names and checksum. - Processing software revision and parameters. - Metrics, observations, failures and conclusions.

Do not overwrite raw data. Keep raw and processed datasets separate.

6. V1 exit criteria#

V1 is successful when the team can: - Acquire repeatable data from both sensors. - Calibrate the sensors into a shared coordinate frame. - Establish and quantify timestamp alignment. - Produce a fused or jointly interpreted spatial representation. - Compare output against a documented reference/ground truth. - Identify where each sensor helps, fails or adds no meaningful value. - Recommend the next experiment based on evidence.

7. Explicit non-goals#

  • Freeze final sensor vendors/models.
  • Design a custom LiDAR ASIC or optical engine.
  • Freeze final handheld enclosure or industrial design.
  • Claim final accuracy from vendor marketing specifications.
  • Start tooling or production before the architecture is validated.

8. Work that can start before any hardware arrives (added in 0.3)#

A substantial part of V1 needs no sensors. This work is on the critical path, is cheap, and is the part most likely to be skipped in the enthusiasm to buy hardware.

Activity Reference Why it comes first
Data schema, frame and time conventions Architecture §2.3 Changing this after data exists invalidates the data
Evaluation harness, validated on a public dataset Software plan Phase S0 A harness that cannot reproduce a known answer cannot be trusted on Falcon data
Checkpoint isolation in software (SW-06) V1-00 §7.7 Makes ground-truth leakage mechanically impossible
Software bill of materials and licence review (LIC-01) Software plan §7 A copyleft dependency discovered late threatens the IP model
M1 scale bar / dimensional artefact V1-00 §7.8 Cheapest insurance against gross scale and transform errors
Tolerance confirmation with Sunrack project practice Tolerances §8 May reset the entire requirement set
Laser-safety and radio-module strategy Compliance plan §5 Constrains architecture; cheap now, expensive later

The tolerance confirmation deserves particular attention. If Sunrack's structures are installed with clamp adjustment that absorbs ±25 mm, survey accuracy beyond that buys nothing — and the whole sensor-selection debate changes. That question can be answered from existing project records this week, with no hardware and no budget.

9. Forward phases beyond V1 (added in 0.3)#

Indicative, and each gated on the previous one. The purpose is to make the path from experiment to product visible, not to commit to dates.

Phase Purpose Entry condition Key output
V1 Feasibility, calibration, synchronisation, measurand characterisation V1-00 readiness gate Measured performance per measurand; evidence-based requirements
V2 Architecture candidate — integrated sensor carrier, embedded compute, battery; fewer cables, no laptop V1 gates D and E assessed; mass/performance trade decided (F-5); FR-05 resolved Validated architecture; thermal and power envelope
V3 Engineering prototype — enclosure, ergonomics, operator interface, in-scan feedback (FR-11) V2 architecture validated; compliance strategy set Design suitable for DFM review
V4 Pre-production — DFM with the manufacturing partner, production calibration, certification campaign V3 validated; partner engaged; FTO opinion obtained Manufacturing data package; certifications
Production Manufacture to the approved design under the OEM model Certification complete; production test proven Product

Gating conditions that must not be bypassed:

  1. Do not enter V2 until the mass-versus-performance trade (F-5) is decided on evidence and FR-05 is resolved. Both change the architecture.
  2. Do not enter V3 until the compliance strategy is set. Laser classification, enclosure and radio choices constrain industrial design.
  3. Do not enter V4 until a freedom-to-operate opinion exists. Handheld SLAM scanning is patent-dense, and a redesign at V4 is far more costly than at V2.

The solar-layer software — roof to mounting-structure design — proceeds in parallel throughout and is not gated on hardware. Per the IP strategy §2, that layer is where the defensible value sits, and it can be developed and even sold against third-party scan data while Falcon hardware matures.