Decisions capture the project direction at the time made. They may be revisited when evidence changes.
| ID | Decision / direction | Rationale | Status |
|---|---|---|---|
| D-001 | Long-term goal is an integrated handheld spatial-scanning device, initially for solar/rooftop use. | Final product intent explicitly clarified by project owner. | Current |
| D-002 | Use a prototype-first R&D approach with commercially available hardware. | The final sensor and hardware architecture are not yet known; experiments should inform it. | Current |
| D-003 | Start experiments with one 3D LiDAR plus one stereo/depth camera. | Practical initial combination for exploring spatial data and sensor fusion. Not a frozen architecture. | Current |
| D-004 | Do not optimize early R&D purchases purely for low price. | Quality and usable developer access are more important than lowest cost at this stage. | Current |
| D-005 | Require usable data access and an open/documented integration path for candidate sensing components. | Falcon needs to implement its own processing/fusion pipeline. | Current |
| D-006 | SHARE3DCAM scanner was rejected as a Falcon sensing platform; retain only as a reference/benchmark. | Earlier vendor support response shared by the project owner stated no third-party raw/intermediate access and no SDK/API/developer interface. | Superseded for current assessment — see D-013 |
| D-007 | Livox, Ouster and Orbbec are active LiDAR vendor candidates. | All have product lines relevant to 3D LiDAR R&D; exact SKUs still require technical validation. | Under evaluation |
| D-008 | Orbbec is also an active stereo/depth camera candidate. | It has both stereo/depth-camera and LiDAR product portfolios. | Under evaluation |
| D-009 | Stereolabs and Luxonis are active stereo/depth camera candidates. | Developer-oriented depth-camera products and SDK ecosystems were identified. | Under evaluation |
| D-010 | Ouster is currently the project owner's personal preference among LiDAR vendors. | Owner is attracted to the industrial LiDAR platform; preference is not a technical selection. | Preference, not selection |
| D-011 | Final device should be manufactured by a third party while product-specific IP is retained by the project/company. | Avoids need to own a factory while preserving product ownership. Requires legal structure. | Strategic intent |
| D-012 | Do not freeze the finished product shape or complete hardware specification now. | Final form factor and architecture should emerge from validated R&D and product requirements. | Current |
| D-014 | Run Prototype V1 in both a controlled indoor mock-roof environment and an actual rooftop, using an independent survey reference and held-out checkpoints as defined in V1-00. | The project owner confirmed both environments and site access. The protocol separates registration-control targets from independent check points and requires reference uncertainty to be assessed before accuracy claims. | Current — protocol defined; instrument/survey support to be arranged |
1. Reopened vendor assessment#
| ID | Decision / direction | Rationale | Status |
|---|---|---|---|
| D-013 | Reopen SHARE3DCAM qualification as a two-track evaluation: (A) offline dataset / algorithm R&D and (B) live device / SDK integration. SHARE is not selected or approved for procurement. | The S20 page advertises an Open SDK and microsecond-level synchronization; a SHARE-published C1 community case describes a ROSBAG package with point-cloud frames, IMU, camera images, timestamps and calibration data. The C1 example does not prove S20 compatibility or live S20 streaming. The exact model behind the earlier negative support response is also unknown. | Open — offline data path promising on C1; S20 live SDK unverified |
D-013 evidence, boundaries and closure criteria#
Official SHARE evidence reviewed 24 November 2026
- SHARE SLAM S20 store page advertises an Open SDK for device communication, data transfer and operational control. The same page advertises microsecond-level system-wide hardware time synchronization. Neither statement alone identifies the live data APIs, externally exposed timestamps or host platforms.
- SHARE community article, published 15 July 2026, describes a SHARE C1 user and a data package containing ROSBAG point-cloud frames, IMU, camera images and timestamps; frame_pose.txt; raw GNSS observations; calibration / extrinsics; point-cloud preview; project metadata and logs. This is model-specific evidence for the C1 workflow, not proof of an identical S20 export.
- SHARE developer page lists Android MSDK 5.17.0 (8 January 2026). Its public description does not establish direct sensor-stream access or Linux support.
- SHARE LCC Unity SDK page describes Unity-based 3DGS rendering and interaction functions; this is not evidence of a LiDAR/IMU acquisition SDK.
- Third-party pose2colmap project demonstrates downstream processing of SHARE C1 exports. It is not an official SDK and does not prove live sensor access or S20 compatibility.
- The earlier vendor support response shared by the project owner said there was no SDK/API and no direct third-party raw/intermediate access, but its exact model, hardware revision and firmware are not established.
Falcon assessment - Offline datasets may be useful for algorithm R&D if SHARE supplies a complete package from the exact model under evaluation. The published C1 case does not establish the S20 data schema. - Live device integration remains unverified until SHARE provides the Open SDK, documentation and a working demonstration of the required streams on Falcon's intended host. - A decoded point-cloud frame is not necessarily a raw LiDAR packet. Falcon must identify the processing stage, timestamp semantics, deskewing/filtering and dependency on SHARE SLAM.
Closure criteria 1. Confirm the exact model, hardware revision and firmware for the old support response and any new SDK offer. 2. Obtain and inspect a complete raw-data package from the exact offered model, with ROSBAG topic definitions, camera / IMU data, timestamps, calibration and logs. 3. Obtain the S20 Open SDK package, API reference, sample code, supported OS/CPU list and license terms. 4. Demonstrate live data access, acquisition control and timing on Falcon's intended Ubuntu host if live integration is claimed. 5. Confirm commercial R&D / product-use permissions and whether Falcon can implement its own calibration, synchronization, SLAM and fusion pipeline.
D-006 remains historical evidence of the earlier assessment. D-013 records the later public evidence and the two-track reassessment. Neither decision authorizes procurement.
2. Decisions arising from the error-budget analysis#
Added in version 0.5. All trace to the Error Budget and Feasibility Analysis, which is analysis rather than measurement — so each of these is open to revision by V1 results, under the falsification conditions in that document's §12.
| ID | Decision / direction | Rationale | Status |
|---|---|---|---|
| D-015 | Replace the single ±2 cm target with tiered, measurand-specific, length-dependent tolerances in the ±(a + b·L) form. | The ±2 cm figure named no measurand, range or derivation. Published comparisons put mature handheld SLAM products at 10–30 mm, degrading to 10–60 mm outdoors, so a blanket ±2 cm would commit Sunrack to beating the industry's best outdoors. See Measurement Requirements. | Current |
| D-016 | Re-scope the stereo camera away from ranging. Evaluate it for texture, colour, edges, semantics, short-range geometry and odometry support. | Finding F-1: depth error grows as z². Reaching ±20 mm at 10 m needs a ~1.9 m baseline against ~0.2 m available. Geometric limit, not a sensor-quality limit. | Current |
| D-017 | Add a photogrammetry / structure-from-motion track as a distinct processing path (path P). | Finding F-2: a walking operator supplies the large effective baseline a handheld rig cannot. This is the open question stereo was wrongly expected to answer. | Current |
| D-018 | Treat sub-millisecond synchronisation and per-point timestamps as hard procurement filters, not scored attributes. | Findings F-8 and F-9: at 30 °/s panning a 10 ms offset gives 52 mm error at 10 m; undeskewed frames smear ~524 mm at 10 m. Software-only timestamping disqualifies a sensor for the product. | Current |
| D-019 | Add angular precision and shutter type as mandatory comparison fields. | Finding F-4: for compact LiDAR the angular term (26 mm at 10 m) exceeds the headline range precision. Finding F-3: rolling shutter skews under rotation, and the current lead stereo candidate has a rolling-shutter RGB sensor. | Current |
| D-020 | Specify Falcon as a relative-accuracy instrument with an optional georeferenced mode. | Absolute accuracy requires surveyed control or RTK, which contradicts the minimal-setup product promise. Mounting-structure engineering overwhelmingly needs relative dimensions. | Proposed — requires owner decision |
| D-021 | Own the interfaces, schema, calibration model, evaluation harness and solar layer; treat pose estimation as a replaceable component behind a stable interface. | Confines open-source licence risk, permits honest algorithm comparison, and avoids coupling the product to one implementation in a fast-moving field. | Current |
| D-022 | Resolve purlin/rafter locatability before architecture freeze (FR-05, Experiment H). | Finding F-12: the tightest genuine tolerance in MMS work concerns members concealed beneath roof sheeting, invisible to any optical sensor. Determines whether Falcon is a complete or partial survey solution. | Open — gates product scope |
| D-023 | Decide the LiDAR mass-versus-performance trade on evidence, after V1. | Finding F-5: the better-performing wide-FOV class is roughly twice the mass of the compact class and alone exceeds the <300 g sensor budget. The owner's stated Ouster preference and the product mass target are in direct conflict. | Open — requires owner decision |
| D-024 | No third-party software component enters the product path without a recorded licence review (LIC-01). | Several well-known open-source SLAM implementations are copyleft. Shipping GPL-derived firmware can oblige source release, directly undermining the IP-ownership model. Most likely IP risk to materialise and the easiest to avoid. | Current |
| D-025 | Raise the independent checkpoint minimum from 12 to 25, and enforce checkpoint isolation in software. | At n = 12 the standard error on RMSE is 20 %, so 20 mm and 25 mm are indistinguishable; conformance to 20 mm would require an observed 14.2 mm. Marginal survey cost is small. | Current |
| D-026 | Adopt three-tier metrology (M1 workshop / M2 local / M3 full survey); only M3 supports an absolute-accuracy claim. | Survey-grade reference for every iteration is unaffordable, and an unaffordable protocol gets bypassed. | Current |
Decisions requiring the project owner#
Three entries above are not settled and need an explicit decision:
- D-020 — relative-accuracy instrument with optional georeferencing. Shapes the product claim and the architecture.
- D-022 — product scope, pending Experiment H. Determines whether Falcon is a complete survey solution.
- D-023 — the mass-versus-performance trade, which runs against a stated vendor preference.
D-023 should be recorded candidly: the owner's expressed preference for Ouster is technically well-founded on angular precision and vertical field of view (Finding F-4 shows an order-of-magnitude advantage), and that same class consumes the entire sensor mass budget. Both facts are true. The analysis suggests the compact class is probably sufficient for the Tier B and C measurands that carry most of the commercial value — but that should be demonstrated in V1, not assumed, and a third option exists: use the higher-grade sensor as an R&D reference instrument and a compact sensor in the product.
3. Important non-decisions#
- No LiDAR model has been selected.
- No stereo-camera model has been selected.
- No final pair has been approved for purchase.
- No system-level accuracy claim has been validated.
- No final form factor, mass, battery or processor has been selected.
- No manufacturing partner has been selected.
- No detailed IP assignment/manufacturing agreement has been drafted.
- No tolerance has been confirmed against Sunrack project practice — every value in the tolerance document is Derived, not Confirmed.
- No freedom-to-operate opinion has been obtained.
- No compliance applicability determination has been made.
4. Change control#
When a decision changes: 1. Add a new row with a new ID. 2. State what changed and why. 3. Link relevant experiment/vendor evidence. 4. Mark the earlier decision as superseded where relevant. 5. Update affected documents without deleting the decision history.
Source: docs/07-governance/DECISION_LOG.md