1. Why the ±2 cm target has to be replaced#
The ±2 cm figure entered the project as a round number, not as a derived requirement. It has three defects:
- It names no measurand. A 20 mm error on a roof area is negligible; on a pre-cut rail it is a site problem; on a single georeferenced coordinate it is beyond the state of the art outdoors.
- It names no range or baseline. Measurement error is range-dependent for every sensing modality under consideration.
- It is not derived from anything. No downstream engineering task was consulted to produce it.
The last point is the real problem. A measurement requirement should come from the decision the measurement feeds. This document derives tolerances from what Sunrack's mounting-structure engineering actually does with roof data, then checks each against what the error budget says is achievable.
The requirement must be fit for the engineering decision it supports — no tighter, and no looser. Over-specifying accuracy is as damaging as under-specifying it: it inflates cost, mass and scan time, and it commits the company to a claim it may not be able to defend.
2. Requirement identifiers and status vocabulary#
Every requirement carries a stable ID so that it can be traced through test and result. See the Requirements Traceability Matrix.
| Prefix | Meaning |
|---|---|
| MR- | Measurement requirement — an accuracy or tolerance requirement on a named measurand |
| FR- | Functional requirement — something the system must do |
| PR- | Product requirement — a physical, power, environmental or usability property |
| DR- | Data requirement — something a sensor or interface must expose |
| Status | Meaning |
|---|---|
| Derived | Traced to a stated engineering need; not yet confirmed with project practice |
| Confirmed | Agreed against real Sunrack project requirements |
| Validated | Demonstrated by Falcon measurement under a documented protocol |
| Aspirational | A target with no evidence it is achievable; must not be quoted externally |
No requirement in this document is Validated. That is the purpose of the V1 campaign.
3. How tolerance is expressed#
Accuracy is stated as a length-dependent pair, in the convention used for survey instruments:
tolerance = ± ( a + b · L )
where a is a fixed term in millimetres and b a proportional term in mm per metre of separation L between the two features being measured. A specification of ±(10 mm + 1 mm/m) therefore means ±20 mm over 10 m and ±40 mm over 30 m.
Each requirement also states:
| Attribute | Why it is needed |
|---|---|
| Measurand | Point, distance, plane offset, plane normal, area, or angle |
| Frame | Relative (within one scan) or absolute (georeferenced) |
| Statistic | RMSE, 95th percentile, or maximum — with the sample size it is claimed over |
| Conditions | Range band, surface type, illumination, operator motion |
A number without all four is not a requirement and must not be quoted.
4. Derivation from mounting-structure engineering#
Each row traces a tolerance to the engineering consequence of getting it wrong.
4.1 Usable area and module count#
Drives the proposal, the bill of materials quantity and the revenue estimate.
A 50 mm boundary error on a 20 m roof edge changes the computed area by about 1 m² on 200 m² — roughly 0.5 %, well inside normal design margin. Module count changes only when a whole row or column marginally fits.
The real risk is not the error, it is the silent marginal case. A row that the scan says fits by 30 mm, and the roof says does not, becomes a site problem. The requirement is therefore as much about reporting as about accuracy.
- MR-01 — Roof boundary, relative: ±(25 mm + 1 mm/m). Derived.
- MR-02 — Usable roof area: ±2 % of computed area. Derived.
- FR-01 — Where a module row or column fits within 150 mm of the available dimension, the system shall flag it as marginal and require manual confirmation rather than reporting a count silently. Derived.
FR-01 is worth more commercially than another 10 mm of accuracy, and it costs nothing but software.
4.2 Roof plane pitch#
Drives structure tilt, leg and rafter lengths, and wind-load assumptions.
Pitch error propagates into fabricated length. Over a span:
| Span | 0.5° error | 1.0° error | 2.0° error |
|---|---|---|---|
| 2 m | 17 mm | 35 mm | 70 mm |
| 3 m | 26 mm | 52 mm | 105 mm |
| 5 m | 44 mm | 87 mm | 175 mm |
A 1° pitch error over a 3 m span produces a 52 mm height error — enough to matter for a pre-fabricated structure. At 0.5° it is 26 mm, which site adjustment absorbs.
Pitch also affects yield, but far more weakly: a 1° tilt error changes annual energy by well under 1 %. The structural requirement is the binding one, not the yield requirement.
- MR-03 — Roof plane normal (pitch and azimuth), relative: ±0.5° for any plane with at least 2 m extent and adequate point support. Derived.
- MR-04 — Roof plane azimuth for yield estimation: ±2°. Derived.
The error budget Finding F-6 shows plane normals should reach roughly 0.03° from random noise on a 3 m patch — a margin of more than ten times against MR-03. MR-03 is comfortably achievable, and the residual risk is systematic bias, not noise.
4.3 Plane flatness and local deviation#
Drives whether a roof needs packing or levelling under rails, and whether ponding is a risk on a flat RCC roof.
- MR-05 — Plane offset / local flatness deviation, relative: ±25 mm. Derived.
4.4 Obstacle position and height#
Drives layout keep-outs and shading losses.
Height error matters through shadow length, which is height divided by the tangent of solar altitude:
| Solar altitude | Shadow / height | Shadow error from 50 mm height error |
|---|---|---|
| 15° | 3.73 | 187 mm |
| 25° | 2.14 | 107 mm |
| 30° | 1.73 | 87 mm |
| 45° | 1.00 | 50 mm |
At low winter sun a 50 mm height error becomes a 190 mm shadow error. Since row-spacing design already carries a margin far larger than that, 50 mm is adequate — but the sensitivity multiplier should be stated in the shading report so that the user can see how height uncertainty propagates.
- MR-06 — Obstacle height, relative: ±50 mm. Derived.
- MR-07 — Obstacle plan position: ±100 mm. Derived.
- MR-08 — Parapet height, relative: ±25 mm — tighter than MR-06 because first-row setback depends directly on it. Derived.
- FR-02 — Shading output shall state the shadow-length sensitivity to height uncertainty at the design solar altitude. Derived.
4.5 Obstacle detectability#
Separate from accuracy, and limited by sampling rather than precision.
Error-budget Section 5.2: at 10 m with 0.7° channel spacing, point spacing is 122 mm, so a 100 mm object can fall between beams.
- FR-03 — The system shall reliably detect and represent roof obstacles with a minimum dimension of 150 mm within the stated working range, under a defined scan path. Derived.
- FR-04 — The system shall report regions where point support falls below the density needed to satisfy FR-03, rather than presenting sparse regions as empty roof. Derived.
FR-04 matters more than it looks. An unflagged data gap reads as free roof area, and free roof area becomes modules in a proposal.
4.6 Prefabrication dimensions — the hard case#
Drives rail cutting and clamp placement. Rails are pre-cut, and clamps must land on purlins or rafters.
- MR-09 — Structural member position, relative: ±15 mm over a 5 m span. Aspirational.
MR-09 is marked Aspirational deliberately. Error-budget Finding F-12 establishes that on a sheet-metal roof the structural members lie beneath the sheet and are invisible to any optical sensor. No scanner accuracy addresses this.
- FR-05 — The project shall determine, before architecture freeze, whether purlin and rafter positions can be inferred from visible evidence (fastener lines, sheet profile, deflection) to within MR-09, or whether this measurement remains a separate manual task. Derived.
FR-05 is a scope-defining investigation, not a nice-to-have. Its outcome decides whether Falcon is a complete survey solution or a partial one — and that changes the product claim and the customer workflow.
4.7 Far-field shading context#
Drives shading from adjacent buildings, towers and trees at 20–50 m.
Loose tolerance, long range — a different sensing regime from everything above, and possibly a different sensor or method.
- MR-10 — Far-field object position and height at 20–50 m: ±500 mm. Derived.
4.8 Absolute georeferencing#
Needed for site drawings, multi-roof campuses, regulatory submissions and revisits.
- MR-11 — Absolute horizontal and vertical position in a site frame, optional mode: ±50 mm with surveyed control, or RTK GNSS where sky view permits. Derived.
Error-budget Section 10: absolute accuracy without control is not achievable, because pose drift dominates. MR-11 is therefore conditional on control or RTK, and must be an optional mode, not a default claim.
5. Consolidated tolerance table#
| ID | Measurand | Frame | Tolerance | Statistic | Tier | Status | Feasibility |
|---|---|---|---|---|---|---|---|
| MR-01 | Roof boundary | Relative | ±(25 mm + 1 mm/m) | RMSE | B | Derived | Achievable |
| MR-02 | Usable roof area | Relative | ±2 % | RMSE | B | Derived | Achievable |
| MR-03 | Plane normal — pitch, azimuth | Relative | ±0.5° | RMSE | C | Derived | Achievable, large margin |
| MR-04 | Azimuth for yield | Relative | ±2° | RMSE | C | Derived | Achievable |
| MR-05 | Plane offset / flatness | Relative | ±25 mm | RMSE | B | Derived | Achievable |
| MR-06 | Obstacle height | Relative | ±50 mm | 95th pct | B | Derived | Probably achievable |
| MR-07 | Obstacle plan position | Relative | ±100 mm | 95th pct | B | Derived | Achievable |
| MR-08 | Parapet height | Relative | ±25 mm | RMSE | B | Derived | Marginal |
| MR-09 | Structural member position | Relative | ±15 mm over 5 m | 95th pct | A | Aspirational | Not achievable optically |
| MR-10 | Far-field object, 20–50 m | Relative | ±500 mm | 95th pct | D | Derived | Achievable |
| MR-11 | Absolute position, optional mode | Absolute | ±50 mm | RMSE | B | Derived | Achievable with control |
| MR-12 | General local distance, L ≤ 10 m | Relative | ±(10 mm + 1 mm/m) | RMSE | B | Derived | Marginal — key V1 question |
Tier definitions#
| Tier | Character | Commercial weight | Technical risk |
|---|---|---|---|
| A | Prefabrication-critical, ±10–20 mm | High value, narrow use | Highest — may be optically impossible |
| B | Layout and quantity, ±25–100 mm | Highest — most of the value | Moderate, achievable |
| C | Angular, ±0.5–2° | High | Lowest — large margin |
| D | Far-field context, ±500 mm | Moderate | Low, different regime |
The strategic read. Most of the commercial value sits in Tiers B and C, and the error budget says both are achievable with candidate hardware. Tier A is the risky tier and may not be optically accessible at all.
This substantially de-risks the programme compared with a blanket ±2 cm commitment — but only if the requirement set is restructured this way, and only if Tier A is resolved explicitly rather than assumed.
6. Requirements the measurement tolerances imply#
These follow from the error budget and are not negotiable independently of it.
| ID | Requirement | Source |
|---|---|---|
| DR-01 | Each sensor shall expose hardware timestamps with documented semantics — acquisition time, not host arrival time. | F-8 |
| DR-02 | Inter-sensor synchronisation shall be better than 1 ms, by hardware trigger or PTP. Software-only timestamping is insufficient for the product. | F-8 |
| DR-03 | LiDAR shall expose per-point timestamps to permit deskewing. | F-9 |
| DR-04 | An IMU shall be available at ≥200 Hz with documented axes, units and calibration, time-aligned to DR-02. | F-9 |
| DR-05 | Raw or minimally processed measurements shall be accessible, with the processing stage documented. | existing D-005 |
| DR-06 | Camera used for feature tracking, colourisation or photogrammetry shall be global shutter. | F-3 |
| DR-07 | Extrinsic calibration shall be readable and writable, with explicit source and destination frames, units and conventions. | F-10 |
| FR-06 | The processing pipeline shall implement per-point motion compensation as a specified, testable stage. | F-9 |
| FR-07 | Edges, ridges, boundaries and parapet lines shall be derived by fitting and intersecting planes, never by selecting extreme points. | F-7 |
| FR-08 | Boresight calibration residual shall be held to ≤0.05° and verified at 8–15 m, not only at calibration-target range. | F-10 |
| FR-09 | Every reported dimension shall carry an uncertainty estimate; bare numbers shall not be exported. | §3 |
| FR-10 | The system shall distinguish relative from absolute measurements in its output and shall not present a relative measurement as georeferenced. | §4.8 |
FR-09 deserves emphasis. A device that reports "12.47 m" invites a trust it has not earned. One that reports "12.47 m ± 0.03 m" is an engineering instrument, defensible in front of an EPC's engineer, and it converts the error budget from an internal document into a customer-facing advantage.
7. Product requirements requiring re-derivation#
The earlier working targets were aspirations, not derived requirements. They are retained here as Aspirational and flagged where the error budget shows a conflict.
| ID | Target | Status | Note |
|---|---|---|---|
| PR-01 | Device mass < 1 kg | Aspirational | Conflicts with the preferred LiDAR class (F-5). Decide the trade after V1-00. |
| PR-02 | Sensor mass < 300 g | Aspirational | Same conflict. |
| PR-03 | System power < 15 W | Aspirational | Host compute inclusion undefined — must be stated. |
| PR-04 | Battery runtime ≥ 2 h | Aspirational | Workload undefined. Specify as scans or area per charge. |
| PR-05 | Scan duration ~1 min | Aspirational | Meaningless without roof area. Restate as area per minute with a closure requirement. |
| PR-06 | Maximum useful range 25 m | Aspirational | Achievable for Tier D only; not at Tier B tolerance. |
| PR-07 | Working range 2–15 m | Derived | Consistent with the error budget for LiDAR. |
| PR-08 | Horizontal FOV ≥ 90°, vertical ≥ 60° | Derived | Wide vertical FOV is genuinely valuable for handheld roof work. |
| PR-09 | Operating temperature 0–50 °C | Derived | Indian rooftop conditions may exceed this; a rooftop surface in summer sun is hotter than ambient. Verify. |
| PR-10 | Ingress protection IP54+ | Derived | Reasonable for outdoor site use. |
| PR-11 | Laser safety Class 1 to IEC 60825-1 | Mandatory | Non-negotiable for a handheld consumer-facing instrument. See the compliance plan. |
PR-05 and PR-09 need particular attention. A one-minute scan time with no stated area is not a requirement at all, and an operating-temperature ceiling of 50 °C may be optimistic for a device held above a sun-exposed Indian rooftop in May.
8. What must be confirmed with Sunrack project practice#
Every tolerance above is Derived, not Confirmed. Converting them requires answers that only Sunrack's own project data can give:
- What survey method is used today on MMS projects, and what does it cost in time and money per roof?
- How often does a mounting structure require site rework because the survey was wrong, and what does an instance cost?
- What dimension, in practice, is the one that causes site problems most often?
- Are rails and structures cut to measure in the factory, or adjusted on site? This single answer determines whether Tier A matters at all.
- For a sheet-metal roof, how is purlin position established today? (Directly determines FR-05.)
- What tolerance does the fabrication process itself hold? A survey tolerance tighter than the fabrication tolerance is wasted.
- What do EPC customers ask for in a survey deliverable, and do any specify an accuracy?
Question 6 is the one most likely to reset the whole requirement set. If structures are fabricated to ±5 mm but installed with ±25 mm of adjustment in the clamps, then survey accuracy beyond about 25 mm buys nothing — and the ±2 cm target was close to right for the wrong reason, while being unnecessary for most measurands.
9. Change control#
This document supersedes the working-target table in Product Intent and Working Requirements §3. That table is retained there as historical record with a pointer here.
When a requirement changes:
- Keep the ID. Never silently redefine what an ID means.
- Record the previous value, the new value and the evidence.
- Update the Requirements Traceability Matrix.
- Add a row to the Decision Log if the change alters project direction.
A requirement moves from Derived to Confirmed only with a stated source in Sunrack project practice, and from Confirmed to Validated only with Falcon measurement under V1-00 metrology rules and leakage controls.
Source: docs/01-requirements/MEASUREMENT_REQUIREMENTS_AND_TOLERANCES.md