SUNRACK TECHNOLOGIES LLP · PROJECT FALCON

Measurement Requirements and Tolerances

Proposed requirement baseline — derived from solar/MMS engineering use, awaiting confirmation against Sunrack project practice

Document ID

FALCON-REQ-002

Version

0.1

Status

Proposed requirement baseline — derived from solar/MMS engineering use, awaiting confirmation against Sunrack project practice

Supersedes

the single ±2 cm working target in Product Intent and Working Requirements §3


1. Why the ±2 cm target has to be replaced#

The ±2 cm figure entered the project as a round number, not as a derived requirement. It has three defects:

  1. It names no measurand. A 20 mm error on a roof area is negligible; on a pre-cut rail it is a site problem; on a single georeferenced coordinate it is beyond the state of the art outdoors.
  2. It names no range or baseline. Measurement error is range-dependent for every sensing modality under consideration.
  3. It is not derived from anything. No downstream engineering task was consulted to produce it.

The last point is the real problem. A measurement requirement should come from the decision the measurement feeds. This document derives tolerances from what Sunrack's mounting-structure engineering actually does with roof data, then checks each against what the error budget says is achievable.

The requirement must be fit for the engineering decision it supports — no tighter, and no looser. Over-specifying accuracy is as damaging as under-specifying it: it inflates cost, mass and scan time, and it commits the company to a claim it may not be able to defend.


2. Requirement identifiers and status vocabulary#

Every requirement carries a stable ID so that it can be traced through test and result. See the Requirements Traceability Matrix.

Prefix Meaning
MR- Measurement requirement — an accuracy or tolerance requirement on a named measurand
FR- Functional requirement — something the system must do
PR- Product requirement — a physical, power, environmental or usability property
DR- Data requirement — something a sensor or interface must expose
Status Meaning
Derived Traced to a stated engineering need; not yet confirmed with project practice
Confirmed Agreed against real Sunrack project requirements
Validated Demonstrated by Falcon measurement under a documented protocol
Aspirational A target with no evidence it is achievable; must not be quoted externally

No requirement in this document is Validated. That is the purpose of the V1 campaign.


3. How tolerance is expressed#

Accuracy is stated as a length-dependent pair, in the convention used for survey instruments:

   tolerance  =  ± ( a  +  b · L )

where a is a fixed term in millimetres and b a proportional term in mm per metre of separation L between the two features being measured. A specification of ±(10 mm + 1 mm/m) therefore means ±20 mm over 10 m and ±40 mm over 30 m.

Each requirement also states:

Attribute Why it is needed
Measurand Point, distance, plane offset, plane normal, area, or angle
Frame Relative (within one scan) or absolute (georeferenced)
Statistic RMSE, 95th percentile, or maximum — with the sample size it is claimed over
Conditions Range band, surface type, illumination, operator motion

A number without all four is not a requirement and must not be quoted.


4. Derivation from mounting-structure engineering#

Each row traces a tolerance to the engineering consequence of getting it wrong.

4.1 Usable area and module count#

Drives the proposal, the bill of materials quantity and the revenue estimate.

A 50 mm boundary error on a 20 m roof edge changes the computed area by about 1 m² on 200 m² — roughly 0.5 %, well inside normal design margin. Module count changes only when a whole row or column marginally fits.

The real risk is not the error, it is the silent marginal case. A row that the scan says fits by 30 mm, and the roof says does not, becomes a site problem. The requirement is therefore as much about reporting as about accuracy.

  • MR-01 — Roof boundary, relative: ±(25 mm + 1 mm/m). Derived.
  • MR-02 — Usable roof area: ±2 % of computed area. Derived.
  • FR-01 — Where a module row or column fits within 150 mm of the available dimension, the system shall flag it as marginal and require manual confirmation rather than reporting a count silently. Derived.

FR-01 is worth more commercially than another 10 mm of accuracy, and it costs nothing but software.

4.2 Roof plane pitch#

Drives structure tilt, leg and rafter lengths, and wind-load assumptions.

Pitch error propagates into fabricated length. Over a span:

Span 0.5° error 1.0° error 2.0° error
2 m 17 mm 35 mm 70 mm
3 m 26 mm 52 mm 105 mm
5 m 44 mm 87 mm 175 mm

A 1° pitch error over a 3 m span produces a 52 mm height error — enough to matter for a pre-fabricated structure. At 0.5° it is 26 mm, which site adjustment absorbs.

Pitch also affects yield, but far more weakly: a 1° tilt error changes annual energy by well under 1 %. The structural requirement is the binding one, not the yield requirement.

  • MR-03 — Roof plane normal (pitch and azimuth), relative: ±0.5° for any plane with at least 2 m extent and adequate point support. Derived.
  • MR-04 — Roof plane azimuth for yield estimation: ±2°. Derived.

The error budget Finding F-6 shows plane normals should reach roughly 0.03° from random noise on a 3 m patch — a margin of more than ten times against MR-03. MR-03 is comfortably achievable, and the residual risk is systematic bias, not noise.

4.3 Plane flatness and local deviation#

Drives whether a roof needs packing or levelling under rails, and whether ponding is a risk on a flat RCC roof.

  • MR-05 — Plane offset / local flatness deviation, relative: ±25 mm. Derived.

4.4 Obstacle position and height#

Drives layout keep-outs and shading losses.

Height error matters through shadow length, which is height divided by the tangent of solar altitude:

Solar altitude Shadow / height Shadow error from 50 mm height error
15° 3.73 187 mm
25° 2.14 107 mm
30° 1.73 87 mm
45° 1.00 50 mm

At low winter sun a 50 mm height error becomes a 190 mm shadow error. Since row-spacing design already carries a margin far larger than that, 50 mm is adequate — but the sensitivity multiplier should be stated in the shading report so that the user can see how height uncertainty propagates.

  • MR-06 — Obstacle height, relative: ±50 mm. Derived.
  • MR-07 — Obstacle plan position: ±100 mm. Derived.
  • MR-08 — Parapet height, relative: ±25 mm — tighter than MR-06 because first-row setback depends directly on it. Derived.
  • FR-02 — Shading output shall state the shadow-length sensitivity to height uncertainty at the design solar altitude. Derived.

4.5 Obstacle detectability#

Separate from accuracy, and limited by sampling rather than precision.

Error-budget Section 5.2: at 10 m with 0.7° channel spacing, point spacing is 122 mm, so a 100 mm object can fall between beams.

  • FR-03 — The system shall reliably detect and represent roof obstacles with a minimum dimension of 150 mm within the stated working range, under a defined scan path. Derived.
  • FR-04 — The system shall report regions where point support falls below the density needed to satisfy FR-03, rather than presenting sparse regions as empty roof. Derived.

FR-04 matters more than it looks. An unflagged data gap reads as free roof area, and free roof area becomes modules in a proposal.

4.6 Prefabrication dimensions — the hard case#

Drives rail cutting and clamp placement. Rails are pre-cut, and clamps must land on purlins or rafters.

  • MR-09 — Structural member position, relative: ±15 mm over a 5 m span. Aspirational.

MR-09 is marked Aspirational deliberately. Error-budget Finding F-12 establishes that on a sheet-metal roof the structural members lie beneath the sheet and are invisible to any optical sensor. No scanner accuracy addresses this.

  • FR-05 — The project shall determine, before architecture freeze, whether purlin and rafter positions can be inferred from visible evidence (fastener lines, sheet profile, deflection) to within MR-09, or whether this measurement remains a separate manual task. Derived.

FR-05 is a scope-defining investigation, not a nice-to-have. Its outcome decides whether Falcon is a complete survey solution or a partial one — and that changes the product claim and the customer workflow.

4.7 Far-field shading context#

Drives shading from adjacent buildings, towers and trees at 20–50 m.

Loose tolerance, long range — a different sensing regime from everything above, and possibly a different sensor or method.

  • MR-10 — Far-field object position and height at 20–50 m: ±500 mm. Derived.

4.8 Absolute georeferencing#

Needed for site drawings, multi-roof campuses, regulatory submissions and revisits.

  • MR-11 — Absolute horizontal and vertical position in a site frame, optional mode: ±50 mm with surveyed control, or RTK GNSS where sky view permits. Derived.

Error-budget Section 10: absolute accuracy without control is not achievable, because pose drift dominates. MR-11 is therefore conditional on control or RTK, and must be an optional mode, not a default claim.


5. Consolidated tolerance table#

ID Measurand Frame Tolerance Statistic Tier Status Feasibility
MR-01 Roof boundary Relative ±(25 mm + 1 mm/m) RMSE B Derived Achievable
MR-02 Usable roof area Relative ±2 % RMSE B Derived Achievable
MR-03 Plane normal — pitch, azimuth Relative ±0.5° RMSE C Derived Achievable, large margin
MR-04 Azimuth for yield Relative ±2° RMSE C Derived Achievable
MR-05 Plane offset / flatness Relative ±25 mm RMSE B Derived Achievable
MR-06 Obstacle height Relative ±50 mm 95th pct B Derived Probably achievable
MR-07 Obstacle plan position Relative ±100 mm 95th pct B Derived Achievable
MR-08 Parapet height Relative ±25 mm RMSE B Derived Marginal
MR-09 Structural member position Relative ±15 mm over 5 m 95th pct A Aspirational Not achievable optically
MR-10 Far-field object, 20–50 m Relative ±500 mm 95th pct D Derived Achievable
MR-11 Absolute position, optional mode Absolute ±50 mm RMSE B Derived Achievable with control
MR-12 General local distance, L ≤ 10 m Relative ±(10 mm + 1 mm/m) RMSE B Derived Marginal — key V1 question

Tier definitions#

Tier Character Commercial weight Technical risk
A Prefabrication-critical, ±10–20 mm High value, narrow use Highest — may be optically impossible
B Layout and quantity, ±25–100 mm Highest — most of the value Moderate, achievable
C Angular, ±0.5–2° High Lowest — large margin
D Far-field context, ±500 mm Moderate Low, different regime

The strategic read. Most of the commercial value sits in Tiers B and C, and the error budget says both are achievable with candidate hardware. Tier A is the risky tier and may not be optically accessible at all.

This substantially de-risks the programme compared with a blanket ±2 cm commitment — but only if the requirement set is restructured this way, and only if Tier A is resolved explicitly rather than assumed.


6. Requirements the measurement tolerances imply#

These follow from the error budget and are not negotiable independently of it.

ID Requirement Source
DR-01 Each sensor shall expose hardware timestamps with documented semantics — acquisition time, not host arrival time. F-8
DR-02 Inter-sensor synchronisation shall be better than 1 ms, by hardware trigger or PTP. Software-only timestamping is insufficient for the product. F-8
DR-03 LiDAR shall expose per-point timestamps to permit deskewing. F-9
DR-04 An IMU shall be available at ≥200 Hz with documented axes, units and calibration, time-aligned to DR-02. F-9
DR-05 Raw or minimally processed measurements shall be accessible, with the processing stage documented. existing D-005
DR-06 Camera used for feature tracking, colourisation or photogrammetry shall be global shutter. F-3
DR-07 Extrinsic calibration shall be readable and writable, with explicit source and destination frames, units and conventions. F-10
FR-06 The processing pipeline shall implement per-point motion compensation as a specified, testable stage. F-9
FR-07 Edges, ridges, boundaries and parapet lines shall be derived by fitting and intersecting planes, never by selecting extreme points. F-7
FR-08 Boresight calibration residual shall be held to ≤0.05° and verified at 8–15 m, not only at calibration-target range. F-10
FR-09 Every reported dimension shall carry an uncertainty estimate; bare numbers shall not be exported. §3
FR-10 The system shall distinguish relative from absolute measurements in its output and shall not present a relative measurement as georeferenced. §4.8

FR-09 deserves emphasis. A device that reports "12.47 m" invites a trust it has not earned. One that reports "12.47 m ± 0.03 m" is an engineering instrument, defensible in front of an EPC's engineer, and it converts the error budget from an internal document into a customer-facing advantage.


7. Product requirements requiring re-derivation#

The earlier working targets were aspirations, not derived requirements. They are retained here as Aspirational and flagged where the error budget shows a conflict.

ID Target Status Note
PR-01 Device mass < 1 kg Aspirational Conflicts with the preferred LiDAR class (F-5). Decide the trade after V1-00.
PR-02 Sensor mass < 300 g Aspirational Same conflict.
PR-03 System power < 15 W Aspirational Host compute inclusion undefined — must be stated.
PR-04 Battery runtime ≥ 2 h Aspirational Workload undefined. Specify as scans or area per charge.
PR-05 Scan duration ~1 min Aspirational Meaningless without roof area. Restate as area per minute with a closure requirement.
PR-06 Maximum useful range 25 m Aspirational Achievable for Tier D only; not at Tier B tolerance.
PR-07 Working range 2–15 m Derived Consistent with the error budget for LiDAR.
PR-08 Horizontal FOV ≥ 90°, vertical ≥ 60° Derived Wide vertical FOV is genuinely valuable for handheld roof work.
PR-09 Operating temperature 0–50 °C Derived Indian rooftop conditions may exceed this; a rooftop surface in summer sun is hotter than ambient. Verify.
PR-10 Ingress protection IP54+ Derived Reasonable for outdoor site use.
PR-11 Laser safety Class 1 to IEC 60825-1 Mandatory Non-negotiable for a handheld consumer-facing instrument. See the compliance plan.

PR-05 and PR-09 need particular attention. A one-minute scan time with no stated area is not a requirement at all, and an operating-temperature ceiling of 50 °C may be optimistic for a device held above a sun-exposed Indian rooftop in May.


8. What must be confirmed with Sunrack project practice#

Every tolerance above is Derived, not Confirmed. Converting them requires answers that only Sunrack's own project data can give:

  1. What survey method is used today on MMS projects, and what does it cost in time and money per roof?
  2. How often does a mounting structure require site rework because the survey was wrong, and what does an instance cost?
  3. What dimension, in practice, is the one that causes site problems most often?
  4. Are rails and structures cut to measure in the factory, or adjusted on site? This single answer determines whether Tier A matters at all.
  5. For a sheet-metal roof, how is purlin position established today? (Directly determines FR-05.)
  6. What tolerance does the fabrication process itself hold? A survey tolerance tighter than the fabrication tolerance is wasted.
  7. What do EPC customers ask for in a survey deliverable, and do any specify an accuracy?

Question 6 is the one most likely to reset the whole requirement set. If structures are fabricated to ±5 mm but installed with ±25 mm of adjustment in the clamps, then survey accuracy beyond about 25 mm buys nothing — and the ±2 cm target was close to right for the wrong reason, while being unnecessary for most measurands.


9. Change control#

This document supersedes the working-target table in Product Intent and Working Requirements §3. That table is retained there as historical record with a pointer here.

When a requirement changes:

  1. Keep the ID. Never silently redefine what an ID means.
  2. Record the previous value, the new value and the evidence.
  3. Update the Requirements Traceability Matrix.
  4. Add a row to the Decision Log if the change alters project direction.

A requirement moves from Derived to Confirmed only with a stated source in Sunrack project practice, and from Confirmed to Validated only with Falcon measurement under V1-00 metrology rules and leakage controls.

Source: docs/01-requirements/MEASUREMENT_REQUIREMENTS_AND_TOLERANCES.md